Q4 2023

Steel Structures, External Infrastructure & 50% Phase One

(Oct–Dec 2023)

Major Achievements

  • 40% completion of Phase One (Nov 2023)
  • 50% completion of Phase One (Dec 2023)

Production Hub (Plot 1)

  • First-floor slabs expanded.
  • Ground-floor to first-floor structural alignment advanced.
  • Tank structural works finalised.
  • External road & corridor preparation progressed.
  • Boundary walls extended.

Storage Hub (Plot 2)

  • Pilot storage completed.
  • Covered storage reached 70% by December.
  • Steel structure installation expanded significantly.
  • External roads, compaction, utilities advanced.

Overall: 2023 ended with a very strong construction momentum.