Q3 2025

BCC Obtained & Tenant Handover

(July – September 2025)

Production Hub (Plot 1)

Authority Approvals

  • Civil Defence inspection passed
  • Electrical and MEP approvals cleared
  • Infrastructure sign-offs completed

Major Milestone

▶ 14 August 2025 – Building Completion Certificate (BCC) Officially Obtained

Tenant Handover

▶ End of September 2025 – Industrial units handed over to tenants

  • Tenants begin moving in machinery and equipment
  • Power supply activated for fit-out works
  • Safety inductions conducted
  • Internal customisation initiated

This phase marks the start of tenant activation and operational buildup.