(Jul–Sep 2023)
Production Hub (Plot 1)
- Footing casting finalised across all blocks.
- Neck columns progressed rapidly.
- Tie-beam works advanced for structural integrity.
- Ground-floor columns erected.
- First-floor slab works initiated.
- Underground water tank excavation & dewatering executed.
- Tank wall rebar and shuttering completed.
- Boundary wall works commenced.
Storage Hub (Plot 2)
- Footings and neck columns fully completed.
- Tie beams constructed with steel & shutter setting.
- Ground-floor columns erected; first-floor slab work initiated.
- Underground tanks reinforced with raft and wall systems.
- Boundary wall and external compacting advanced.
- Steel structure installation started.
Overall: Major superstructure progress on both hubs set the stage for rapid 2024 growth.