Q3 2023

First Vertical Rise: Columns, Slabs & Underground Tanks

(Jul–Sep 2023)

Production Hub (Plot 1)

  • Footing casting finalised across all blocks.
  • Neck columns progressed rapidly.
  • Tie-beam works advanced for structural integrity.
  • Ground-floor columns erected.
  • First-floor slab works initiated.
  • Underground water tank excavation & dewatering executed.
  • Tank wall rebar and shuttering completed.
  • Boundary wall works commenced.

Storage Hub (Plot 2)

  • Footings and neck columns fully completed.
  • Tie beams constructed with steel & shutter setting.
  • Ground-floor columns erected; first-floor slab work initiated.
  • Underground tanks reinforced with raft and wall systems.
  • Boundary wall and external compacting advanced.
  • Steel structure installation started.

Overall: Major superstructure progress on both hubs set the stage for rapid 2024 growth.