(April – June 2025)
Production Hub (Plot 1)
This quarter achieved the most significant milestone in the Production Hub’s construction lifecycle.
Construction Completion
- All civil, structural, architectural, and MEP works completed
- Heavy-duty industrial flooring fully installed
- External roads, truckways, and interlock areas completed
- Final façade finishes delivered across all units
- Utility rooms and LV/MV networks commissioned
- Internal lighting, fire safety, and electrical systems activated
- Drainage and water networks tested and approved
Commissioning & Authority Preparation
- Full testing of fire systems, alarms, hydrants
- Electrical energisation and load testing
- Plumbing and drainage performance validations
- Safety and compliance inspections conducted
- Submission of all documentation (as-builts, certifications, test reports)
Milestone
▶ July 2025 – Production Hub construction formally completed and submitted for BCC inspection