Q2 2025

Production Hub Construction Completion & BCC Submission

(April – June 2025)

Production Hub (Plot 1)

This quarter achieved the most significant milestone in the Production Hub’s construction lifecycle.

Construction Completion

  • All civil, structural, architectural, and MEP works completed
  • Heavy-duty industrial flooring fully installed
  • External roads, truckways, and interlock areas completed
  • Final façade finishes delivered across all units
  • Utility rooms and LV/MV networks commissioned
  • Internal lighting, fire safety, and electrical systems activated
  • Drainage and water networks tested and approved

Commissioning & Authority Preparation

  • Full testing of fire systems, alarms, hydrants
  • Electrical energisation and load testing
  • Plumbing and drainage performance validations
  • Safety and compliance inspections conducted
  • Submission of all documentation (as-builts, certifications, test reports)

Milestone

▶ July 2025 – Production Hub construction formally completed and submitted for BCC inspection