(Apr–Jun 2024)
Production Hub (Plot 1)
- Upper slab works and roof framing advanced.
- Blockwork internal walls initiated.
- Extensive MEP installations began (fire, electrical, plumbing).
Storage Hub (Plot 2)
- Covered storage 90–95% complete.
- Roofing and cladding progresses rapidly.
- Internal finishes (floor topping, drainage channels) installed.
- Weighbridge base works completed.
- All utility network installations progressed.
Overall: Storage Hub moved toward finalisation for Q3 2024 completion.