Q2 2023

PCC, Footings & Structural Reinforcement Starts

(Apr–Jun 2023)

Production Hub (Plot 1)

  • PCC casting for footings completed in several blocks.
  • Bitumen waterproofing applied on PCC layers.
  • Steel and shuttering works for footings prepared.
  • Neck column initial reinforcement started.

Storage Hub (Plot 2)

  • PCC casting for footings completed plot-wide.
  • Bitumen applied to PCC and footings.
  • Neck columns cast and tie-beam preparation started.
  • External roadworks (backfilling & compaction) began.

Overall: Foundations across both hubs were stabilised for vertical construction.