(Apr–Jun 2023)
Production Hub (Plot 1)
- PCC casting for footings completed in several blocks.
- Bitumen waterproofing applied on PCC layers.
- Steel and shuttering works for footings prepared.
- Neck column initial reinforcement started.
Storage Hub (Plot 2)
- PCC casting for footings completed plot-wide.
- Bitumen applied to PCC and footings.
- Neck columns cast and tie-beam preparation started.
- External roadworks (backfilling & compaction) began.
Overall: Foundations across both hubs were stabilised for vertical construction.