Q1 2025

Storage Hub Commissioning & Production Hub Construction Progress

(January – March 2025)

Storage Hub (Plot 2) – Commissioning & Launch

Following its structural completion in September 2024, Q1 2025 was dedicated to commissioning, system approvals, and operational readiness.

Commissioning Works

  • Full installation and load testing of 40MT & 20MT overhead cranes
  • Final calibration of weighbridges (18m & 30m / 150MT)
  • Fire alarm & firefighting networks tested and approved
  • CCTV, access control, and monitoring systems activated
  • External traffic markings and pedestrian pathways completed
  • Electrical energisation, lighting installation, and hydrant network verified
  • SOPs and logistics workflows finalised
  • Operational team training and mobilisation

🎉 Storage Hub Grand Opening

▶ 25 February 2025 – Official Launch & Start of Operations

  • Full activation of all covered, open, oversized, and vertical storage areas
  • First incoming cargo handled under new operational protocols
  • Metal Park’s logistics ecosystem officially begins operations

Watch Metal Park - Storage Hub Grand Opening Viceo

Production Hub (Plot 1) – Active Construction Continuation

While Q1 had no major certification or handover milestones, it represented a critical continuity phase between Q4 2024 and the major construction completion in Q2 2025.

Works Progressed in Q1 2025

Building on the near-finalised structural and MEP works of Q4 2024:

Structural & Architectural

  • Completion of remaining blockwork and partition walls
  • Continuation of internal plastering and first-coat painting
  • Finalisation of steel roof elements and remaining cladding installation
  • Door frames, window systems, and façade components installed across remaining units

MEP & Utilities

  • Progress of fire protection installation across all units
  • First-fix and second-fix MEP completion in multiple bays
  • Electrical cable pulling, DB installation, and energisation preparation
  • HVAC and ventilation systems installation advanced
  • Mechanical drainage lines finalised
  • Waterline connections prepared for testing

External Works

  • Continuation of truckway corridors and interlock pavement
  • Completion of concrete loading corridors
  • Light pole bases, external lighting cabling, and hydrant installations progressed
  • Landscaping base preparations advanced
  • Connection of external utilities ahead of Q2 commissioning

Summary of Q1 2025 for Production Hub

Construction activities in Q1 maintained momentum, closing out the remaining civil and architectural scopes and driving MEP works toward the finish line in preparation for full construction completion in Q2 2025.