Q1 2023

Groundwork, Soil Improvement & Full Mobilisation

(Jan–Mar 2023)

Production Hub (Plot 1)

  • Full mobilisation of machinery and site teams.
  • Soil improvement, backfilling, and early compaction works.
  • Setting-out and grid marking completed.
  • PCC preparation for footing zones initiated.

Storage Hub (Plot 2)

  • Site clearance and early earthworks completed.
  • Soil treatment and compaction executed across major blocks.
  • PCC base preparation for footings commenced.

Overall: Q1 established all ground conditions necessary for deeper structural work.