(Jan–Mar 2023)
Production Hub (Plot 1)
- Full mobilisation of machinery and site teams.
- Soil improvement, backfilling, and early compaction works.
- Setting-out and grid marking completed.
- PCC preparation for footing zones initiated.
Storage Hub (Plot 2)
- Site clearance and early earthworks completed.
- Soil treatment and compaction executed across major blocks.
- PCC base preparation for footings commenced.
Overall: Q1 established all ground conditions necessary for deeper structural work.