(Jul–Sep 2024)
MAJOR MILESTONE: Storage Hub fully constructed – September 2024
Production Hub (Plot 1)
- Roof installation and steel frames completed across blocks.
- MEP systems advanced into mid-stage installation.
- External road and corridor networks shaped.
Storage Hub (Plot 2) – CONSTRUCTION COMPLETE
- All structures, roofing, cladding and steel frames completed.
- 96 covered bins + 16 open units + oversized bays completed.
- Weighbridges installed (18m & 30m, 150MT).
- Fire systems, lighting, and CCTV installed.
- External yards paved and marked.
Although structurally complete in September 2024, the following still needed time:
- Overhead crane installation
- Testing & commissioning
- Operational setup
- Safety sign-offs
- Final authority approvals
- Tenant coordination
- Internal system integration